docs: archive completed cc-ci build loops
This commit is contained in:
+2
-1
@@ -1,6 +1,6 @@
|
||||
# archive/ — how cc-ci and its orchestrator were built and moved, before the combined host
|
||||
|
||||
Historical record only. Nothing in here is deployed or evaluated. It was moved out of the live
|
||||
Historical record. Original-build compatibility launch files are linked from `cc-ci-plan/`; the Nix unit reads those paths but the completed loops do not run. It was moved out of the live
|
||||
tree on 2026-09-07 when the CI server and the orchestrator were consolidated onto one Hetzner
|
||||
host (`nixosConfigurations.cc-ci` in `../flake.nix`; deploy guide in `../README.md`; the plan
|
||||
that did it is `../cc-ci-plan/plan-cc-ci-combined-host.md`).
|
||||
@@ -16,6 +16,7 @@ that did it is `../cc-ci-plan/plan-cc-ci-combined-host.md`).
|
||||
| `plans/plan-orchestrator-hetzner-migration.md` | Incus VM → Hetzner `cpx22` move of the orchestrator (2026-05-31). Has the reboot-resilience design (`cc-ci-loops.service`). |
|
||||
| `plans/plan-migrate-cc-ci-to-hetzner.md`, `plans/plan-cc-ci-hetzner-migration.md`, `plans/plan-cc-ci-hetzner-terraform.md` | The CI server's own move from the `cc-nix-test` Incus VM to Hetzner `cpx32` (`91.98.47.73`, 2026-05-31), and the terraform that provisioned it (lives in the cc-ci repo). |
|
||||
| `plans/plan-repo-consolidation.md` | The earlier repo layout consolidation. |
|
||||
| `original-build/` | Completed Builder/Adversary phase plans, prompts, launchers, original agent instructions, and the first combined-host build guide. See its README. |
|
||||
|
||||
The cc-ci server's own history (machine-docs, decisions, the clean-room rebuild that proved
|
||||
"two repos + one age key + one `nixos-rebuild switch`") is in the cc-ci repo under
|
||||
|
||||