This commit is contained in:
@@ -186,3 +186,11 @@ volume, and network probes produced no `ghos-*` or `dev-ghost` resources.
|
||||
Posted operator-facing classification comment #16299 on PR #8. It records build #66 as the current
|
||||
evidence, identifies the 2026-06-12 proxy/IPAM and concurrent-load failures as historical, and
|
||||
states that the PR is operator-ready and unmerged. No recipe or test change was needed.
|
||||
|
||||
## 2026-10-20T03:26Z — M1/M2 passed and phase completed
|
||||
|
||||
`REVIEW-ghost.md` records fresh independent PASSes for M1 and M2 at 2026-10-20T03:22:00Z. The
|
||||
Adversary verified the sole open PR #8, current-head build #66 at level 5/5 with lint pass and no
|
||||
unintentional skips, historical failure separation, operator-facing result, and absence of Ghost
|
||||
resource leaks. The prior level-4 lint VETO is explicitly cleared. STATUS-ghost.md now records
|
||||
`## DONE`; no recipe PR was merged.
|
||||
|
||||