review(ghost): fail current gates on leak and closed PR
continuous-integration/drone/push Build is failing
continuous-integration/drone/push Build is failing
This commit is contained in:
@@ -322,3 +322,36 @@ Ghost resources are clean.
|
||||
final-state explanation.
|
||||
- M2 remains unverified until a fresh current-head retry is completed and PR#9 receives
|
||||
the required classification/readiness explanation.
|
||||
|
||||
## Fresh gate verification — 2026-11-23T18:26:00Z
|
||||
|
||||
### M1: FAIL
|
||||
|
||||
- Cold Gitea comments confirm exact `!testme` comment #16787 on PR #9's head
|
||||
`256c0f879bc4b64bf321161c1e8bb3338b826058`; result comment #16788 links build #173.
|
||||
- Cold host artifact `/var/lib/cc-ci-runs/173/results.json` confirms `recipe=ghost`, `pr=9`,
|
||||
ref `256c0f879bc4`, level 5, and install/upgrade/backup/restore/custom/lint all `pass`, with
|
||||
no unintentional skips.
|
||||
- However, the artifact fields `clean_teardown` and `no_secret_leak` are `null`, not the
|
||||
expected `true` values in STATUS-ghost's M1 acceptance inputs.
|
||||
- Independent Swarm probe finds leaked volume
|
||||
`warm-ghost_ci_commoninternet_net_ghost_content`; no matching stack or service exists.
|
||||
This violates the required clean post-run state. Proxy subnet is `10.10.0.0/16`.
|
||||
|
||||
### M2: FAIL
|
||||
|
||||
- Cold Gitea inventory now shows **zero** open Ghost upgrade PRs: PR #9 was closed at
|
||||
`2026-11-23T18:22:19Z` after comment #16799 said it was upstreamed and closing. PRs #1-#8
|
||||
are also closed. The phase requires exactly one operator-ready open upgrade PR, so the
|
||||
current state does not satisfy M2.
|
||||
- Comment #16795 does provide the requested historical classification and says PR #9 is
|
||||
unmerged, but the subsequent closure and leaked volume leave the phase not operator-ready.
|
||||
|
||||
### Verdict
|
||||
|
||||
M1 and M2 FAIL. The current build is a genuine level-5 lifecycle pass and the historical
|
||||
proxy/load classification is present, but the acceptance state has an untracked leaked Ghost
|
||||
volume, missing teardown/leak-proof metadata, and no open operator-ready Ghost upgrade PR.
|
||||
Do not write `## DONE` until the resource is accounted for/removed, the result metadata is
|
||||
explained or corrected by a fresh run, and the required single open PR state is restored or
|
||||
the phase plan is explicitly revised by the operator.
|
||||
|
||||