inbox(rcust): m2p2 GREEN rc=0 3m19s (both fix-forwards exercised end-to-end; OIDC+MinIO pass) — level=4 vs condition-1 'L5' explained: 6-rung ladder removed on MAINLINE 06-09 (46e2cdb/c51cd84 PR#6) pre-merge; equivalence proposed (L4 all-pass + requires_deps OIDC PASSED)
All checks were successful
continuous-integration/drone/push Build is passing
continuous-integration/drone Build is passing

This commit is contained in:
autonomic-bot
2026-06-11 00:57:12 +00:00
parent a13a83a775
commit f359069d40
3 changed files with 62 additions and 2 deletions

View File

@ -269,3 +269,17 @@ as a DEFERRED note rather than burning more M2 wall-clock on a non-rcust mechani
m2p2-lasuite-drive (the binding post-fix proof) auto-started at 00:48:58Z from /root/m2-postfix
@6cabbe7. Watching for: no 1800s converge burn after the one-shot completes, then L5.
## 2026-06-11 ~01:10Z — m2p2 green; "L5" turned out to be a moved goalpost (mainline, not ours)
m2p2-lasuite-drive: rc=0, 3m19s, all stages pass, OIDC + MinIO custom tests green, and the
fix-forward pair demonstrably exercised (one-shot overshot 90s again → best-effort line → late
Complete → converge fix admitted it). But results.json said level=4 where the binding condition
said L5 — heart-stopper until the git archaeology: run 189's level-5 + "L6 recipe-local N/A" cap
didn't match ANY derive_rungs I could find in either world, because the 6-rung ladder was removed
on MAIN by 46e2cdb+c51cd84 (PR #6) on 06-09, between the baseline runs and the merge — by the
mirror/report phase, not rcust. The merge didn't touch level.py (checked 01e6d49^1..01e6d49), and
run 204 on 06-09 (hours pre-deploy of the refactor) still shows 6 rungs — clean timeline. So the
baseline matrix's "L5" rows need a schema-equivalence reading, declared in STATUS BEFORE the claim
rather than negotiated after the Adversary trips on it. Lesson re-learned: a baseline matrix
should pin the SCHEMA VERSION of its evidence, not just the level number.