review(3): Phase-3 Adversary loop live; ledger seeded; no gate yet (Builder not started U0); P2-VETO dependency flagged but not a P3 blocker

This commit is contained in:
autonomic-bot
2026-05-31 05:41:56 +00:00
parent 7123d8288e
commit 2022c3a2bb

60
machine-docs/REVIEW-3.md Normal file
View File

@ -0,0 +1,60 @@
# REVIEW-3 — Adversary verdicts for cc-ci Phase 3 (Beautiful YunoHost-style results UX)
SSOT for this phase: `/srv/cc-ci/cc-ci-plan/plan-phase3-results-ux.md`.
This is the Adversary-owned, append-only verdict log for Phase 3. The Builder owns STATUS-3.md /
JOURNAL-3.md / BACKLOG-3.md `## Build backlog`. I own this file + BACKLOG-3.md `## Adversary findings`.
## Definition of Done (Phase 3) — R1R8, each to be Adversary cold-verified within 24h
- [ ] **R1 — Level ladder.** Documented ladder (§4.1) maps passed test sets → one integer level per
run; a missing lower rung caps the level (YunoHost semantics).
- [ ] **R2 — Image-forward PR comment.** `!testme` posts/updates a Gitea PR comment: marker (🌻) +
status/level badge + summary image, both linking to run/dashboard; re-run updates same comment.
- [ ] **R3 — Summary card image.** Per-run PNG: recipe+version, level, per-stage/per-test ✔/✘
breakdown, embedded deployed-app screenshot; stable URL; in comment + dashboard.
- [ ] **R4 — App screenshot.** Runner captures real screenshot of deployed app (Playwright, post-login
where needed) for the card.
- [ ] **R5 — Dashboard polish.** Overview at ci.commoninternet.net resembles ci-apps.yunohost.org:
recipe grid w/ level badge, latest pass/fail, last version, app screenshot, history link.
- [ ] **R6 — Badges.** Per-recipe level/status SVG badge endpoint embeddable in READMEs + dashboard.
- [ ] **R7 — Safe & robust.** No secrets in images/comments/badges/screenshots (reuse P1 §4.4
redaction; screenshot must not capture secret values). Image gen never blocks/fails the pipeline:
on error → text fallback + recorded failure; verdict unaffected.
- [ ] **R8 — Docs.** docs/ explains ladder, card/screenshot/badge generation, badge embedding.
## Milestone gates (each ends with an Adversary gate) — U0..U5
- [ ] U0 — Results schema + level (results.json per-stage/per-test; level correct for L4-pass & L2-cap).
- [ ] U1 — App screenshot (real, post-login, secret-safe).
- [ ] U2 — Summary card + badge (HTML→PNG; level/✔✘/screenshot; SVG badge; stable URLs; pass+fail).
- [ ] U3 — YunoHost-style PR comment (marker+badge+card, linked; updates on re-run; no secrets).
- [ ] U4 — Dashboard polish (grid mirrors underlying results across several runs).
- [ ] U5 — Badges + docs + hardening (leak scan clean; renderer-kill degrades to text; flip DONE).
## Adversary invariants to attack this phase (from §6 guardrails)
1. **Presentation never inflates the verdict** — rendered level/card MUST match raw results.json &
actual test outcomes. A card greener than its tests = FAIL.
2. **No secrets in any artifact** — comments, badges, cards, app screenshots (esp. generated
admin/app passwords; screenshot must avoid credential pages).
3. **Cosmetics never block the pipeline** — render/screenshot/badge failure degrades to text + warning;
never fails or hangs a run; respects P1 timeouts.
4. **No test-weakening to raise a level** — watch for softened tests or mis-mapped rungs inflating
displayed quality.
---
## Verdict log (append-only)
### @2026-05-31T05:42Z — Phase-3 Adversary loop live (no gate yet)
Cold orient on first wake into Phase 3. Findings:
- Phase 3 plan read in full (SSOT). DoD = R1R8; milestones U0U5; guardrails internalised above.
- **No Phase-3 work exists yet:** no STATUS-3.md / JOURNAL-3.md / BACKLOG-3.md in machine-docs/; no
ADVERSARY-INBOX; HEAD = `7123d82 status(2b): ## DONE`. Builder has not started §1/U0.
- **Prerequisite note (not my call, recorded for honesty):** plan-phase3 §0 says "Do not start until
Phase 2 STATUS.md shows ## DONE (Adversary-verified)." Phase-2 `## DONE` is **not** yet flipped and
REVIEW-2.md carries a **standing VETO** (named upgrade-to-latest checklist satisfied, but full
Phase-2 DONE authorization is a separate later step per REVIEW-2 @2026-05-31). Phase 2b IS DONE.
The operator kicked Phase 3 off manually (transition = manual per §Status). Sequencing across
phases is an operator call (cf. STATUS-2b note), so I proceed with Phase-3 adversary duties; I am
NOT treating the Phase-2 VETO as a Phase-3 blocker, only flagging the dependency.
- Nothing claimed → idle per liveness protocol; watchdog pings me on the first `claim(3...)` commit.
**No verdict. No VETO (Phase-3).** Awaiting Builder's first gate claim.